Only three of 9 expected nuclear reactors completions 2014 were actually completed. There was a slippage of a few months on several which are now mostly expected in the first half of 2015.
The third wave of construction should be completed by mid-2017 and have about 20 more nuclear reactors.
Hongyanhe-3 [1080 MWe CPR) did reach criticality in October. It should begin operation in the next few weeks Hongyanhe-4 should start by the end of 2015.
Two units at the Taishan Nuclear Power Plant are under construction in Chixizhen, Taishan, Guangdong province, China. It was planned to go online in 2013.
Taishan 1 is now expected to be operational June 2015 (1750 MWe)
Taishan 2 is now expected to be operational Sep 2016 (1750 MWe)
These are European Pressurized Reactor (EPR) by Areva
Brian Wang is a Futurist Thought Leader and a popular Science blogger with 1 million readers per month. His blog Nextbigfuture.com is ranked #1 Science News Blog. It covers many disruptive technology and trends including Space, Robotics, Artificial Intelligence, Medicine, Anti-aging Biotechnology, and Nanotechnology.
Known for identifying cutting edge technologies, he is currently a Co-Founder of a startup and fundraiser for high potential early-stage companies. He is the Head of Research for Allocations for deep technology investments and an Angel Investor at Space Angels.
A frequent speaker at corporations, he has been a TEDx speaker, a Singularity University speaker and guest at numerous interviews for radio and podcasts. He is open to public speaking and advising engagements.